Completing a Milestone
1 min
you cannot set the status of a milestone to complete, or 100%, until all of the tasks under it have their status complete if you try to update the status of a milestone to complete or enter 100% in the % done field, the system displays an error message stating that the tasks under it are not all in the complete status if you created the milestone from a template, you cannot set the status of the milestone to complete or 100% if the approval is in pending status the system does not create the associated tasks for the next milestone sequence until the status of the milestone is complete to complete a milestone that you created manually (that is, a milestone that was not created from a release template) sign in to as a open the release workspace open the release record for which you want to create a milestone select the schedule tab values of the % done field for all of the associated tasks for the milestone should be set to 100% to do this a select the milestone b enter 100 in the % done field c in the actual end date field, enter the date of the milestone completion d select save