Step 7 – Test and validate the Ivanti EPMM HA environment
Use this test plan to help you test your Ivanti EPMM HA systems.
Table: Test and validation plan for Ivanti EPMM HA
Task | Description | Steps | Expected Results | Notes |
|---|---|---|---|---|
1 | Check System Connectivity | On Primary server, go to Manage Trusted Hosts > Test Connection (against the Secondary Ivanti EPMM) On Secondary server, go to Manage Trusted Hosts > Test Connection (against the Primary Ivanti EPMM) | Successful results from both tests. | |
2 | Sync systems manually | On Secondary server, go to Select primary from the Primary Ivanti EPMM Hostname menu. Click Run Sync Now. | In Sync History, all tasks show completed with no errors reported. | |
3 | Verify Standby Ivanti EPMM updated correctly | On Secondary server through the CLI Enable mode, start tomcat: >service tomcat start Log on through the Admin portal and confirm the device count matches that in the Primary Ivanti EPMM. | The device count is exactly the same as the Primary. | |
4 | Test Email Notification | On Secondary server, under Notification Settings, enter a valid email and click Test | A test email is sent by the Secondary server. | |
5 | Confirm Heartbeat Process | On Standby server go to Troubleshooting > Logs select MICS > Apply. In View Module Logs select HighAvailability. | The heartbeat activity shows in the HighAvailability window. | |